During the month of May, structural works continued to progress according to the planned schedule. The floor slab between the ground floor and the first floor of Block 1 was successfully completed, marking an important step in the vertical development of this section of the building.
In addition, formwork works for Blocks 2 and 3 were completed, leaving both structures ready for the next concrete pouring phase. These milestones allow the building structure to continue taking shape and support progress into the next phases of construction.
In addition, formwork works for Blocks 2 and 3 were completed, leaving both structures ready for the next concrete pouring phase. These milestones allow the building structure to continue taking shape and support progress into the next phases of construction.