Construction Progress 2025

January 2026

Over the past weeks, construction has continued to progress steadily through the foundation phase of the building. The retaining walls of basement level -2 are now almost complete, with only minor sections remaining to be finished.

Basement level -2 is nearing completion overall, and works have begun on the formwork for the slab between levels -2 and -1, representing another important milestone in the development of Olympic Residences.