During this period, construction has continued to progress steadily in the structural phase of the project. The garage ramp connecting levels -1 and -2 has been completed, representing a key element for the building’s functionality.
Additionally, the slabs between level -1 and the ground floor of Block 2, as well as between level -1 and the semi-basement floor, have been completed, further advancing the structural development across different areas of the project.
Overall, approximately 50% of the structure has now been completed. The remaining structural works are expected to progress at a more consistent pace due to the simpler nature of the remaining structural elements.