During the month of February, we continued making steady progress in the building’s foundation phase. The walls of basement level -2 have now been fully completed, establishing a solid base for the structural development.
In addition, the slab between levels -2 and -1 is almost finished, allowing us to prepare for the next structural works.
In addition, the slab between levels -2 and -1 is almost finished, allowing us to prepare for the next structural works.