Construction Progress Olympic Residences

June 2026

2026
During June, structural works continued to progress at a good pace. In Block 1, the third residential floor was completed, leaving only the final residential floor to complete the above-ground structure of this block.

At the same time, Blocks 2 and 3 continued to progress. Two floors were completed in each block, further advancing the structural framework and allowing the project to move forward into the next stages of construction.